Oil & Gas Projects

oil
Optimizing the process and improving the quality of products in Tehran refinery

Optimizing the process and improving the quality of products in Tehran refinery

Development Percentage
0

%

Optimizing the process and improving the quality of products in Tehran refinery
Client
National Iranian Oil Engineering and Construction Company
Consultant
EIED
Status
Completed
Contract Period
36 Months
Commencement Date
December ,2007

This project is a collaborative project with the aim of reducing the sulfur output of diesel and kerosene production according to European standards (euro-o5) by 10 ppm as an EPC, which includes:
- Design, purchase and construction of a diesel desulfurization unit with a capacity of 53,000 BPSD
- Design, purchase and construction of kerosene desulfurization unit with a capacity of 31,500 BPSD
- Design, purchase and construction of a hydrogen production unit with a capacity of 42 MMSCF
- Design, purchase and construction of sulfur recycling unit with a capacity of 110T/D
- Design, purchase and construction of power generation unit (5x13MW) GTG
- Optimizing the amine unit by increasing the capacity by 16 T/Hr
- Optimizing the sour water separation unit by increasing the capacity to 120 T/Hr
- Optimization of wastewater treatment unit by increasing its capacity to 100T/Hr
- Construction of ancillary facilities including Flare and its appendices, fixed roof and floating roof storage tanks
- Construction of Roman control buildings, power station, power plant, etc.
- Implementation, installation and commissioning of all the mentioned systems and delivery to the employer