oil
Fiber optic project

Fiber optic project

Development Percentage
0

%

Fiber optic project
Client
Iranian Gas Engineering and Development Co.
Consultant
Monenko Iran Engineering Company
Status
Completed
Contract Period
21 Months
Commencement Date
July ,2018

Detailed design project, supply of goods, implementation of optical fiber cable and telecommunication buildings of the North-Northeast gas pipeline of the third segment (as EPC)
- Construction of 435 km long fiber optic cable from Sabzevar to the border of Iran and Turkmenistan
- Design and construction of telecommunication building in all the stations of the pipeline route
- Purchase of equipment and implementation of grounding and lightning arrester system for all buildings of route stations
- Construction of KV20 three-phase power supply network for stations
- Anticipation and provision of all spare parts and consumables for the installation and start-up period and for the two-year maintenance period.