Minab – Bandar Abbas pipeline

Development Percentage
0

%

Minab - Bandar Abbas pipeline
Client
Ministry of Energy - Hormozgan Regional Water Joint Stock Company
Consultant
Hormozgan Regional Water Joint Stock Company
Status
Completed
Contract Period
12 Months
Commencement Date
December ,2000

Design, procurement, construction, transportation and installation of cathodic protection system equipment for the second water supply line from Minab to Bandar Abbas with a length of 100 kilometers, including:
- All earthworks and civil operations, concrete and molding works, painting and metal works
- Supply and installation of rectifier transformer, injection current anodes, isolated parts, anode wellhead equipment, rectifier converters
- Conducting all copper cabling and grounding and test point equipment and setting up and testing the cathodic protection system.