Construction of foundation and installation of seven tanks in Sablan factory

Construction of foundation and installation of seven tanks in Sablan factory

Development Percentage
0

%

Construction of foundation and installation of seven tanks in Sablan factory
Client
Sablan Petrochemical Industries Company
Consultant
Projects Development and Solution Co. (PDSCO)
Status
Completed
Contract Period
10 Months
Commencement Date
April ,2013

The purpose of the implementation of the project to build storage tanks to store process fluids and water in Sablan Petrochemical and includes:
- Construction of concrete and earth foundation and implementation of geomembrane insulation in the bottom of the tanks
- Construction, installation and welding of carbon steel and stainless steel tanks in the amount of about 1300 tons
- Performing N.D.T and radiography operations according to the latest revision of API 650 standard and project standards.
- Performing hydrostatic test operations.
- Sandblasting and painting of all tanks and acid washing of stainless steel tanks