Construction of gas pressure boosting station in Kohdasht

Construction of gas pressure boosting station in Kohdasht

Development Percentage
0

%

Construction of gas pressure boosting station in Kohdasht
Client
Naftanir Industrial Design Company
Consultant
Hirbodan Management Company
Status
Completed
Contract Period
19 months + one year operation period
Commencement Date
June ,2016

The purpose of this project is to build a gas pressure booster station with an approximate capacity of 110 million cubic meters per day and includes the purchase of some items and the implementation and installation of civil and structural equipment, mechanical items, plumbing, electricity and telecommunications, and precision tools as briefly described below. :
- Purchase of various items such as HVAC system, lighting, earthing, part of plumbing items, local distribution board ,etc.
- Landscaping, road construction and fencing and construction of industrial and non-industrial buildings such as control, security, health, administrative and maintenance buildings, generators, air compressors, etc.
- Implementation and installation of mechanical, gas and process equipment including 4 turbo compressors, Air Cooler, Scrubber and air compressor packages, Vent Stack ,etc.
- Installation of gas turbine fuel supply package and gas pressure reduction station building along with all related equipment
- Prefabrication of all parts of the plumbing department such as pipes and fittings, installation of equipment including valves and flanges
- Implementation of piping between the project equipment, performing relevant tests, insulation, rust removal and paint
- Implementation, installation and construction of electrical and telecommunication equipment such as transformers, medium and low voltage panels, lightning arresters, emergency power generators, CCTV, paging, lighting, earthing and related cabling
- Implementation, installation and construction operations in the precision instruments sector, such as the installation of control system equipment, fire alarm system, SCS, Field Instrument and control cabling and precision instruments
- Functional testing operations, pre-launch and 72 hours of project launch