Capacity increase and construction of Bandar Abbas – Isfahan pipelineCapacity increase and construction of Bandar Abbas – Isfahan pipelineCapacity increase and construction of Bandar Abbas – Isfahan pipeline

Capacity increase and construction of Bandar Abbas – Isfahan pipelineCapacity increase and construction of Bandar Abbas – Isfahan pipelineCapacity increase and construction of Bandar Abbas – Isfahan pipeline

Development Percentage
0

%

Capacity increase and construction of Bandar Abbas - Isfahan pipeline
Client
National Iranian Oil Engineering and Construction Company
Consultant
Bina Consulting Engineers / Parsikan Consulting Engineers
Status
Completed
Contract Period
2 Months
Commencement Date
October ,2004

The project of increasing the capacity of the Bandar Abbas-Rafsanjan pipeline and the construction of the 20-product Rafsanjan-Isfahan pipeline and related facilities was carried out by the EPC method and as a partnership, which includes:
1 - Bandar Abbas oil storage
2 - Bandar Abbas pump house
3 - Qutbabad pump house
4 - Mehr Aran house pump
5 - Rafsanjan pump house
- Design, purchase and installation of main and booster process pumps, fire department and utility
- Purchase and implementation of piping and connecting them to existing headers of turbopumps
- Designing, buying and carrying out all electrical operations and precision tools including panels, earthing, transformers, cabling, lighting and control.
- Supply, installation and painting of seven fixed and floating roof storage tank devices in the mentioned sites
- Full implementation of civil works, structures, architecture including buildings, canopies, landscaping and equipment foundation