Implementation of civil operations, piping and installation of Dana Petrochemical

Implementation of civil operations, piping and installation of Dana Petrochemical

Development Percentage
0

%

Implementation of civil operations, piping and installation of Dana Petrochemical
Client
شركت شركت صنايع پتروشيمي دنا
Status
Completed
Contract Period
15 Months
Commencement Date
April ,2020

The project is a part of the implementation of piping, civil works, installation of equipment and metal structure of Dena Methanol plant in Pars Energy Special Economic Zone - Phase 2 of petrochemical projects in Asaluye city of Bushehr province. The construction area is about 70,000 square meters and the daily production capacity of this project is 5000 tons. The services and obligations of the contractor in this project include:
- Implementation of a part of the civil executive operations, including the foundation of pumps, concrete mine steps, tanks and buildings
- Construction of concrete enclosures and hardening of laboratory and warehouse buildings
- Completion of underground piping, implementation of above-ground piping in areas 23 to 26
- Installation of metal structure related to 5004-T and installation of equipment including transformers and pumps 8001 and 7001 and tower 5004 and piping related to specified Tie-ins as well as Accessory & Internal Tray related to towers 5001, 5002, 5003 of the construction Dena Methanol project.